South Station Crew Base
Boston, MA
| Advertisement Date |
10/7/2026 |
| Pre-Bid Meeting Date & Time | 10/22/2026 at 1:00 PM |
| Bid Opening Date | 11/12/2026 |
| Contract Number | F79CN01 |
| Class | 7 - BUILDINGS |
| Project Value | $5,300,000.00 |
| DBE Goal | N/A % |
Scope of Work:
The space is approximately 6,000 SF and located within the basement of the concourse area. The space will serve train operators (40-60 employees) before and after shifts with quiet areas, bathroom facilities, common kitchen, and office areas. The program is to include space for Terminal Operations for employee check-in/out. The existing space is a below grade “shell” space with concrete, steel and CMU construction. Existing utilities and structure (to remain) are exposed in the space. The scope of work includes interfacing with existing structure and systems, including extending or adding MEP/FP systems as required.
All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.
View Complete Notice to Bidders
Comparison of Bids Report for Contract F79CN01 (18.13kb) updated Thursday, November 12, 2026
F79CN01 Planholders List
F79CN01 Planholders List (Printer Friendly)
| Apparent Low Bidder | Bid Amount |
| Emmaty, Inc. | $5,033,468.00 |
| Bid Responses | Bid Amount |
| H J Russell & Company | $5,700,000.00 |
| Wes Construction Corp. | $6,984,000.00 |
| Paul J. Rogan Co. Inc. | $7,999,079.00 |